Depot of North-South Commuter Railway gets 8-month extension | Inquirer News

Depot of North-South Commuter Railway gets 8-month extension

/ 06:09 PM January 24, 2023

Transportation Sec. Jaime Bautista leads the inspection of the depot of the North South Commuter Railway in Clark Freeport, Pampanga on Monday, Jan. 23. (Contributed photo)

Transportation Sec. Jaime Bautista leads the inspection of the depot of the North South Commuter Railway in Clark Freeport, Pampanga on Monday, Jan. 23. (Contributed photo)

CLARK FREEPORT, Pampanga — The Department of Transportation (DOTr) has moved from October 2024 to June 2025 the completion date of the Clark depot here, which will be the site of the operations control center of the 147-kilometer North-South Commuter Railway (NSCR) that was planned to be running next year.

The DOTr on Tuesday (Jan. 24) confirmed giving an eight-month extension to the South Korean contractor POSCO Engineering & Construction, which explained it received the depot’s 36-hectare land on the Mabalacat, Pampanga side of Clark late due to the clearing of several fruit-bearing trees there, Transportation Sec. Jaime Bautista said in a statement.

Article continues after this advertisement

“We promised the President that we will finish the project as agreed on the timeline that we set. I just want to see to it that we work together and finish this project on time,” Bautista said in the statement.

FEATURED STORIES

According to DOTr, the Clark depot was designed to have 33 stabling tracks as parking areas for trains, 12 more tracks to get to maintenance facilities, as well as 48 buildings.

It said over 33 percent of works have been completed as of Dec. 31, 2022.

Article continues after this advertisement

The depot, Bautista said, is “a very important part of the NSCR, considering the operations control center of the project will be located here.”

Article continues after this advertisement

It did not say how the delay in finishing the depot would affect the schedule of rail operations.

Article continues after this advertisement

The NSCR, which came on the heels of two failed railway projects, was finally started during the administration of then President Rodrigo Duterte.

The rail runs from Calamba in Laguna to Clark Freeport in Pampanga, connecting Central Luzon, Metro Manila, and the Southern Tagalog regions. Jointly funded by the Asian Development Bank and the Japan International Cooperation Agency, the National Economic and Development Authority raised the project cost to P777.55 billion in late 2018. INQ

RELATED STORIES:

Target completion of PNR Clark Phase 2 moved to June 2025

DOTr signs contract for 304 more North-South Commuter Railway train cars

JMS
Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: ADB, DoTr, NEDA

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.