Contractor to city: Stop SRP-BRT road clearing project | Inquirer News

Contractor to city: Stop SRP-BRT road clearing project

/ 07:07 AM April 19, 2013

THE winning contractor of the SRP-BRT route clearing and embankment project yesterday requested that the project implementation be suspended.

Engineer Bernabe Gilbor of the Supreme ABF Construction said he found out that the documents of the P50 million project awarded to his company last March 25, were not in order.

“I will wait for the documents to be in order before I start with the project. I will respect and will wait for the go signal of the council,” he said.

Article continues after this advertisement

Gilbor yesterday asked the Department of Engineering and Public Works (DEPW) to issue a suspension order on the clearing and embankment project until concerns on its attachment documents would be clarified and corrected.

FEATURED STORIES

City Council members convened for an executive session yesterday to seek clarification as to why and how the P50 million BRT embankment project was bidded out and awarded to a contractor even in the absence of council authority.

Councilor Jose Daluz III told the council during their regular session on Wednesday that while the POWE preparation for the embankment project did not pass the council, Mayor Michael Rama would have to get City Council approval before he could enter into a contract with Gilbor.

Article continues after this advertisement

However, in yesterday’s executive session, Gilbor admitted to the council that he already entered into a contract with Rama on March 26, a day after the project was awarded to his company. A notice to proceed was also issued to him on April 3.

Article continues after this advertisement

Councilor Augustus Pe Jr., the council’s majority floor leader, questioned the bidding of the project in the absence of an Approved Budget Contract (ABC).

Article continues after this advertisement

He pointed out that the ABC which was attached to project contract lacked the signature of city treasurer Emma Villarete. Instead a Neneta Fernandez, executive assistant 2 under the mayor , wrote a note in the contract certifying the availability of the P50 million for the project.

Mayor Rama said in a separate interview that defects on the contract might be cured by a council ratification

Article continues after this advertisement

“If ever naa na (ang contract) there can be curative means like ratification,” he said.

Councilor Margot Osmeña said that the signed contract would remain illegal and invalid unless approved by the council.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

“Nag bantay lang mi sa kwarta. There is no quarrel on the need for the BRT route clearing and embankment,” she said./Reporter Doris C. Bongcac

TAGS:

No tags found for this post.
Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.