DPWH wants Manila Bay dredging over by July

By: - Reporter / @jovicyeeINQ
/ 05:08 AM April 18, 2019

MANILA, Philippines — The Department of Public Works and Highways (DPWH) said on Wednesday said that it wanted to finish dredging a 1.5-kilometer-long portion of Manila Bay by July in time for the rainy season.

According to Public Works Undersecretary Emil Sadain, the deployment of two more heavy-duty amphibious dredging machines will help fast-track the DPWH’s efforts to remove debris, plastics and other solid waste from the section of the bay between the US Embassy and Manila Yacht Club in Malate.

ADVERTISEMENT

The DPWH earlier said that work on the bay would be divided into five sectors, each one lasting up to 120 days.

Since dredging began last month, “improvements” have been observed in the bay, Sadain noted, adding that the DPWH has so far removed an estimated 18,000 cubic meters of muck and silt.

He said that water tests conducted by the Department of Environment and Natural Resources also showed that the average amount of dissolved oxygen in the bay had improved to a level that would allow aquatic life.

Read Next
LATEST STORIES
MOST READ
Don't miss out on the latest news and information.
View comments

Subscribe to INQUIRER PLUS to get access to The Philippine Daily Inquirer & other 70+ titles, share up to 5 gadgets, listen to the news, download as early as 4am & share articles on social media. Call 896 6000.

TAGS: dpwh, Manila Bay rehabilitation
For feedback, complaints, or inquiries, contact us.


© Copyright 1997-2019 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.