Talisay flyover closed for retrofitting, traffic seen – DPWH
CEBU CITY — The Department of Public Works and Highways in Central Visayas (DPWH-7) has announced the closure of the flyover in Barangay Tabunok, Talisay City from June 9 to 22 for retrofitting and warned residents of traffic congestion in the area.
The closure was announced through flyers sent out by Engineer Leslie Anthony Molina, head of the Cebu 2nd district engineering office.
Retrofitting of its expansion joints worth P20 million is the second phase of the flyover rehabilitation project.
It will be undertaken by the PLD Construction and will last for 14 days.
The closure of the Tabunok flyover is timed with the ongoing dry-run being implemented by the Cebu City Traffic Office in preparation for the construction of an underpass at the intersection of N. Bacalso and
F. Llamas Street.
The construction of the underpass might start on Friday should the dry-run succeed, said DPWH-7 project engineer Roy dela Cruz.
Article continues after this advertisementThe closure of the Tabunok flyover on Friday will be the third this year.
The first one was March 31 to April 2 and the second, April 4 to 5, for phase 1 of the rehabilitation project which included scraping of the existing asphalt and replacing it with new asphalt and water
proofing.
The project amounted to P9 million and was awarded to First Grandeur, Inc. SFM/rga