NGCP: Luzon grid on yellow alert due to forced outage, derated capacity | Inquirer News

NGCP: Luzon grid on yellow alert due to forced outage, derated capacity

/ 01:35 PM December 06, 2022

MANILA, Philippines — Due to forced outages and derated capacities of several power plants, the National Grid Corporation of the Philippines (NGCP) placed the Luzon grid under yellow alert on Tuesday.

The NGCP said that the Luzon grid would be under yellow alert from 1 p.m. to 4 p.m. and 5 p.m. to 6 p.m., as the available capacity is at 11,522 megawatts (MW).

The peak demand is at 10,612 MW, the NGCP said in its advisory.

ADVERTISEMENT

“Four plants are on forced outage, while three others are running on derated capacities, for a total of 2,145 MW unavailable to the grid,” it explained.

FEATURED STORIES

RELATED STORY

NGCP raises yellow alert for Luzon grid

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: grid, Luzon, NGCP, yellow alert

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.