Secure water supply seen by end of 2021

STILL LOW As of Wednesday, the water level at La Mesa Dam is pegged at 75.73 meters above sea level, still over four meters below the spilling level of 80.15 masl. —EDWIN BACASMAS

MANILA, Philippines — Water consumers in eastern Metro Manila and Rizal province can expect a more secure supply, but not until the end of 2021.

Manila Water Co. Inc. on Wednesday announced that it had signed a supply deal with the Metropolitan Waterworks and Sewerage System (MWSS) and Wawa JVCo Inc. for raw water from the Razon group’s Wawa project in Rizal.

Article continues after this advertisement

Wawa JVCo is a joint venture company formed by Prime Metroline Infrastructure Holdings Corp. and San Lorenzo Ruiz Builders and Developers Corp.

FEATURED STORIES

The agreement, which covers a 30-year period, involves the supply of raw water from Wawa and Tayabasan rivers through the Wawa Bulk Water Supply Project, specifically with a dam to be built by the joint venture.

“The first phase will involve the supply of 80 million liters per day (MLD) of raw water by Dec. 31, 2021, while the second phase will involve the supply of an additional 438 MLD of raw water by Dec. 31, 2025,” Manila Water said in a regulatory filing.

Article continues after this advertisement

Medium term

Article continues after this advertisement

It said the Wawa project was one of several measures that had been identified to boost water supply in the medium term for Manila Water’s concession area.

Article continues after this advertisement

Last March, Manila Water signed with Prime Metroline a memorandum of understanding on cooperation for building what water supply authorities were touting as the most immediate available solution to address the shortage.

The MWSS has described the new Wawa Dam that tycoon Enrique K. Razon and builder Oscar Violago are pursuing as the “immediate alternative water source for the metropolis to provide medium-term water security.”

Article continues after this advertisement

The other major solution is the controversial Kaliwa Dam in Quezon province, which can provide 600 MLD but will take longer to build.

The east zone concession area has been under a rotational service interruption program since March when the water level at La Mesa Dam in Quezon City fell below the normal operating level.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

The west zone concession area served by Maynilad Water Service Inc. has been experiencing the same problem after the water level at Angat Dam in Bulacan province dropped below the critical level.

TAGS: MWSS, Wawa JVCo

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.