EDC working 24/7 to restore power in Leyte
Power plants of the Energy Development Corp. (EDC) may be able to restore power supply in Leyte within 10 days when repairs had been done on the damages caused by the magnitude 6.5 earthquake.
READ: EDC shuts down geothermal power plants in Ormoc
“Our team of contractors has been mobilized to work 24/7, safety considerations permitting, to complete the assessment and accelerate return to service,” said in a statement.
“Barring any unforeseen issues, EDC could have about 317 MW (megawatts) of power restored to Leyte within the next 10 days,” it added.
The statement said Energy Secretary Alfonso Cusi inspected the facilities along with EDC president Richard Tantoco, who had been at the site since Friday.
Article continues after this advertisementBased on the ongoing assessment, the Tongonan Geothermal Power Plant Unit 1 may not be operational for some time due to damage to the cooling tower.
Article continues after this advertisementUnit 2 with power capacity of 35 megawatts may be operational in the next seven to 10 days as tests on the unit and the main transformer as well as cooling tower repair needed to be performed.
READ: Leyte quake aftermath: Visayas power reserve plummets
The Upper Mahiao plant would be operational in five to seven days, bringing 132 MW back to the grid.
Units 1 and 2 of the Malitbog power plant were estimated to return to service within the next 7 to 10 days bringing about 150 MW of power back online.
“Unit 3 however, will remain on shutdown due to damage sustained by the cooling tower,” the statement said.
“Access to our Mahanagdong plant remains difficult and we have not yet been able to assess the extent of damage. We are still working to clear landslide debris,” he added.
The marshalling station would be in operation in three to five days since the repair had been started.
Aside from transmitting power from the plants, these repairs will also allow the connection of the station to the 230 kV line to Luzon. JPV