Subic expressway expansion finished by year-end

/ 05:02 AM August 13, 2020

SUBIC BAY FREEPORT, Zambales, Philippines — The P1.6-billion infrastructure project to expand Subic Freeport Expressway (SFEx) is 50-percent complete and will be finished by the end of the year, according to the North Luzon Expressway (NLEx) Corp.

In a statement, NLEx said the road improvement resumed in mid-May after the lifting of enhanced community quarantine in the area.

ADVERTISEMENT

The 8.2-kilometer SFEx connects this free port to the 94-km Subic-Clark-Tarlac Expressway, which in turn links to the Tarlac-Pangasinan-La Union Expressway.

The SFEx expansion includes adding two expressway lanes, two new spans at the Jadjad and Argonaut bridges, and a new tunnel near the existing one to improve traffic flow and road safety.

FEATURED STORIES

—Joanna Rose Aglibot

Read Next
Don't miss out on the latest news and information.

Subscribe to INQUIRER PLUS to get access to The Philippine Daily Inquirer & other 70+ titles, share up to 5 gadgets, listen to the news, download as early as 4am & share articles on social media. Call 896 6000.

TAGS: NLEX Corp., SFEx expansion
For feedback, complaints, or inquiries, contact us.

News that matters

By providing an email address. I agree to the Terms of Use and
acknowledge that I have read the Privacy Policy.



© Copyright 1997-2021 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.