Prepare updates for projects, Cebu City engr’g dept told

/ 07:48 AM December 19, 2012

NO new projects will be approved by the Cebu City Council for next year until the  Department of Engineering and Public Works (DEPW) provides updates of projects funded for implementation this year.

Majority Floor Leader Augustus Pe Jr. pushed  city engineers for this after DEPW officials said only P60 million out of P355 million worth of projects under the Annual Investment Plan (AIP) were bidded out.

Engr. Joel Reston said they’ve so far prepared Programs of Works and Estimates for P237 million of the P355 million infrastructure projects identified under the 2012 Annual Investment Plan (AIP).

Article continues after this advertisement

Only 11 of the projects covered under the AIP were bidded out, he said.

FEATURED STORIES

Councilor Margot Osmeña, who heads the council’s budget committee, questioned why some items were being budgeted even when they cannot be implemented yet.

“We don’t bite more than we can chew…Budget is being tied up there and we might be taking away (funds) from other priority projects,” she said.

Article continues after this advertisement

The council is set to  deliberate today  on the P73 million Supplemental Budget (SB) 3.

Article continues after this advertisement

SB3 includes the P50 million appropriation for the P10,000 bonus for  each of the nearly 5,000 City Hall regular and casual workers.

Article continues after this advertisement

Mayor Michael Rama wanted the SB3 approved for distribution of the additional Christmas bonuses during the city’s Christmas party on Friday afternoon.

In last Monday’s session, the council voiced surprise on why  P170 million for the construction of Carbon Market Unit II projects have not been started yet.

Article continues after this advertisement

DEPW is seeking  a  P10.3 million budget for sewerage and drainage improvements which is P6.8 million more than this year’s appropriation of P3.5 million.

They’re also seeking P110 million for repair and construction of drainage system, up by P10 million in this year’s budget. Engr. June Nadine Sison, chief of DEPW’s construction division, said the P100 million drainage project already has a POWE.

But it has yet to be bidded out, he said. Reston said there were delays in bidding the projects because the City Treasurer’s Office was still processing the Approved Budget Contract for them.

Pe said the DEPW earlier promised to furnish the council with a monthly status update of city government projects.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Sison told the council that they don’t have enough personnel to prepare the reports. The official said they can only issue updates upon request. Chief of Reporters Doris C. Bongcac

TAGS: Cebu, Construction

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.