7 of 8 Vizcaya bridge projects suffer delays | Inquirer News

7 of 8 Vizcaya bridge projects suffer delays

/ 05:04 AM February 10, 2018

BAYOMBONG, Nueva Vizcaya—Seven of eight bridge projects here and in Diadi town under the government’s “Build, Build, Build” infrastructure program have suffered delays, disrupting travel in Cagayan Valley.

The bridge-widening projects along Daang Maharlika, the region’s main highway, had been blamed for a number of road crashes and massive traffic congestion here and in Diadi.

Records from the Department of Public Works and Highways (DPWH) showed that the bridge projects, costing P195 million, had incurred delays, some by as long as seven months.

ADVERTISEMENT

DPWH is expanding the bridges in Barangay Bonfal, Kalungkong, Colocol and Busilac in Bayombong as well as those in Barangay Buaya, Rosario and Oriwong in Diadi by adding two more lanes to the four-lane stretches of the highway.

Only the Rosario Bridge has been completed. —MELVIN GASCON

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Infra, Regions

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.