The Metro Rail Transit Line 3 (MRT-3) experienced two technical glitches that resulted to the unloading of commuters in two different train stations on Monday.
At 6:17 a.m., a southbound train offloaded its passengers at Cubao Station due to a mechanical problem.
The hitch was described “category 2”, which means that the “train (was) removed with replacement.”
At 12:21 p.m. meanwhile, passengers were unloaded at Shaw Station after a northbound train also suffered a technical issue.
The said hiccup was described “category 3”, which means that the train was either “removed without replacement” or that a “cancellation of loops and insertion was made.”
Normal operations resumed once the management addressed the mechanical troubles.
There was, however, no recorded technical problem last Sunday, November 26. /kga