Coal plant delay due to blackout

/ 01:44 AM April 22, 2015

DAVAO CITY—Aboitiz firm Therma South Inc. (TSI) has cited the April 5 blackout that plagued Mindanao as reason for the delay in the commissioning of Unit 2 of its coal-fired power plant in Barangay (village) Binugao in Toril district here.

The unit, with a capacity of 150 megawatts, would have been put online this month, but the power outage, which the National Grid Corp. of the Philippines attributed to a glitch in a switch in Agus in Lanao, damaged the facility’s boiler, TSI president and chief executive officer Benjie Cariaso Jr. said.

“The disruption damaged the auxiliary components of its boiler,” Cariaso said.

“The damage will delay the commercial operation of Unit 2 by about 10 months,” he said, pointing out that repair work on the boiler could last that long. Judy Quiros, Inquirer Mindanao

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Aboitiz, coal-fired plant, News, Regions

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.