Luzon, Visayas power outlook good | Inquirer News

Luzon, Visayas power outlook good

Petilla

Department of Energy Sec. Jericho Petilla. INQUIRER FILE PHOTO

So far so good.

Luzon and the Visayas still can meet the present demand with their available power supply, thus avoiding outages in the two grids, Energy Secretary Jericho Petilla said in a briefing.

ADVERTISEMENT

“The DOE (Department of Energy) has a running four-week estimate which we update regularly. So far, with the temperature not as high as anticipated, and with people cooperating by saving power, Luzon seems OK,” Petilla said.

FEATURED STORIES

And since Luzon is interconnected with the Visayas, the two can share power, so it follows that the Visayas is also “OK,” Petilla said.

Smooth power plant operations and some rainshowers to break the summer heat have helped keep brownouts or power outages at bay in both Luzon and the Visayas.

Short-term outages

But Petilla still would not rule out the possibility of short-term outages or brownouts.

Consumers, he said, should not let their guard down and should keep on saving energy.

“May is historically the peak but we are dealing with power-plant forced outages, which are unpredictable. And we are dealing with the weather, which is also unpredictable. If the heat increases or if summer is extended, we might still have problems,” Petilla said.

ADVERTISEMENT

Experts said the possibility increases after the Holy Week as electricity demand is expected to climb with the rising temperature.

“We still have to watch May, when demand peaks. And we have to watch June and even July because power plants were asked to move their maintenance period to these months in order to avoid summer. If summer gets extended, it could pose risks,” Petilla said.

National Renewable Energy Board Vice Chair Ernesto Pantangco earlier told an energy forum that the critical period from March 15 to April 14 was still under close watch.

“For the past weeks, the temperature increase was not as high as we thought and demand has not been as high as we expected. Hopefully this weather continues. We will see after Holy Week how we will fare,” Pantangco said.

Industry data showed that electricity demand from mid- to end-March had averaged about 7,700 megawatts, which was much lower than the expected 8,600 MW.

After Holy Week, the next critical period will be in May, when demand is estimated to peak at 9,100 MW to 9,400 MW.

“Normally that (peak) happens around the third week of May,” Pantangco said.

Possible rate increase

Energy Regulatory Commission Executive Director Francis Saturnino Juan said it was also possible for power rates to rise due to the fuel shift of gas plants during the temporary shutdown of the Malampaya gas platform from March 14 to

April 15.

If the power situation triggers the Interruptible Load Program (where businesses and industries use their generator sets to ease demand from the Luzon grid), this may also add to the cost of power unless the government decides later to shoulder this additional cost.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Earlier, Philippine Independent Power Producers Association Inc. president Luis Miguel Aboitiz said supply would be tight from end-March to end-June and there could be brownouts if more than one major power plant would go on forced outage (unexpected shutdown), “but the real time to focus on is April 5 to 15.”

TAGS: DoE, Luzon, power, Power supply, Visayas

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.