MMDA to prohibit big vehicles to pass Edsa-Quezon Ave. u-turn
due to scheduled retrofitting

MMDA to prohibit big vehicles to pass Edsa-Quezon Ave. u-turn

/ 07:43 PM June 19, 2024

Buses, trucks and other vehicles with vertical clearance above 2.5 meters will be prohibited from passing the u-turn slot over Edsa Quezon Avenue (Q. Ave.) flyover starting July 22, said the Metropolitan Manila Development Authority (MMDA) on Wednesday.


Metropolitan Manila Development Authority (MMDA) traffic enforcers man a traffic along Edsa in Quezon City in this file photo taken on March 30, 2023. The MMDA will prohibit big vehicles to take the Edsa-Quezon Ave u-turn due to scaffoldings being erected in the area. INQUIRER FILE PHOTO / NIÑO JESUS ORBETA

MANILA, Philippines — Buses, trucks and other vehicles with vertical clearance above 2.5 meters will be prohibited from passing the u-turn slot on Edsa Quezon Avenue (Q. Ave.) starting July 22, said the Metropolitan Manila Development Authority (MMDA) on Wednesday.

According to the MMDA in a traffic advisory, the u-turn slot, both northbound and southbound, will only be passable to light vehicles.

Article continues after this advertisement

“The closure of the u-turn slot is to give way to the installation of scaffolding under the flyover, which will limit the vertical clearance to 2.5 meters only,” the agency said.

FEATURED STORIES

READ: Edsa-Kamuning flyover shut for repairs

The MMDA then advised affected buses and trucks to take alternate routes.

Article continues after this advertisement

Vehicles traveling from Edsa southbound should turn left to Quezon Ave., left at Sen. Miriam Defensor Santiago Ave., left at North Ave., to Mindanao Ave or Edsa to their point of destination.

Article continues after this advertisement

Vehicles traveling from Edsa northbound should go straight towards North Ave, then make a u-turn in front of Quezon City Academy to their point of destination.

Article continues after this advertisement

The MMDA said the scaffolding is part of the Department of Public Works and Highways’ ongoing project of retrofitting or strengthening of permanent bridges.

READ: DOTr: Parts of Mindanao Ave. closed starting June 29 

Article continues after this advertisement

The retrofitting of the Edsa Q. Ave. flyover is expected to be completed on August 4. Felice Nafarrete, INQUIRER.net intern

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: MMDA, U-turn

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.