Maynilad: Water interruptions in Makati, Manila, Pasay from Sept. 30 to Oct. 1
MANILA, Philippines — Portions of Makati City, Manila, and Pasay City will be experiencing water supply interruptions, the Maynilad Water Services Inc. said on Thursday.
In its advisory, Maynilad said that interruptions will occur within a specific number of hours, starting 8:00 p.m. on September 30 to 9:00 p.m. on October 1, 2023.
According to Maynilad, the interruption is due to a maintenance activity involving the replacement of a 1050 mm gate valve at Espiritu Pumping Station and the insertion of a 600 mm valve to allow for the removal of a 750-mm-diameter pipe along Estrada Street from Espiritu to Lemery in Malate, Manila.
Affected areas include the following:
Makati City
- Bangkal
Manila
Article continues after this advertisement- Barangays 719, and 726 to 733 in Malate
- Barangays 745 to 762, 769, 803, and 807 in Sta. Ana
Pasay City
Article continues after this advertisement- Barangays 1 to 7, 9, 14 to 20, 23, 33 to 37, 41 to 49, 51 to 53, 55 to 68, 71 to 75, 80 to 138, and 140 to 143
Maynilad advised its customers to store enough water for the duration of the service interruption.
Upon resuming the water supply, Maynilad also reminded consumers to let the water flow out until it clears before using it.
Maynilad said that the maintenance activity is in line with their efforts to improve water services in the area, mainly to help reduce water losses.
RELATED STORIES
Maynilad earmarks P5.7B for 5 water treatment plants
Metro Manila households face daily water supply cut