Cebu bulk water project ready after 2013 election | Inquirer News

Cebu bulk water project ready after 2013 election

/ 07:31 AM March 24, 2012

THE Carmen bulk water project is targeted for completion on June 2013, a month after the May elections.

By then it will be ready to supply and sell water to potential customers like the Metro Cebu Water District and towns in north Cebu.

Virgilio Rivera of the Manila Water Consortium said negotiations for road right of way and feasibility study validation will proceed in May this year.

Article continues after this advertisement

The Province of Cebu and the Ayala-led consortium signed a joint investment agreement for the P702-million project last March 21 at the Capitol.

FEATURED STORIES

In a briefing, Rivera said the detailed engineering design and approval will be done by June.

A weir and extraction facilities will be built in Luyang River in Carmen town, said Manila Water Consortium president Gerardo Ablaza Jr.

Article continues after this advertisement

A weir is a small dam in a river or stream.

Article continues after this advertisement

“It’s not a dam which is going to be destructive. There will be no displacement of communities, no flooding because it will not be a (high) dam, it will be a weir,” Ablaza said.

Article continues after this advertisement

From the extraction facility, water will be channeled through large pipes to a treatment plant and on to the water district or municipal water supply provider on a bulk water supply basis.

Rivera said they aim to secure an Environmental Compliance Certificate (ECC) in October. The project will start operation in the fourth quarter of 2013.

Article continues after this advertisement

This means actual water supply and sales will take place after the May 2013 local elections.

The Cebu bulk water supply project targets serving central and north Cebu customers—local government units, water districts and other water distributors.

Under the joint investment agreement, the consortium will help develop water supply facilities to deliver bulk water to target cities and towns.

Under a Design-Build-Finance-Operate scheme, the project will deliver 35 million liters per day.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Water from the Luyang River will be treated and stored, then pumped and transmitted to a proposed reservoir in Liloan town. Correspondent Carmel Loise Matus

TAGS:

No tags found for this post.
Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.