LRT-2 on scaled down operations for two weekends

LRT-2 suspends operations after fire hits Santolan Station

FILE PHOTO/INQUIRER/Grig C. Montegrande

MANILA, Philippines — The Light Rail Transit Line 2 (LRT-2) will scale down operations for two consecutive weekends this month in preparation for the opening of the LRT-2 East Extension Project.

In an advisory on Friday, the Light Rail Transit Authority (LRTA) said operations be be scaled down or limited on May 22 and 23 and on May 29 and 30.

“During these dates, train service will only be available from Araneta-Center Cubao to Recto station and vice versa,” LRTA said.

“This is to give way for the integration test of the signaling system of the Line 2 East Extension (Marikina and Antipolo Stations) with the existing Line 2 System from Santolan to Recto,” it added.

LRTA said opening hours will remain from 5:00 a.m. to 8:30 p.m. for the Cubao – Recto route.

The last trip, meanwhile, will be at 9:00 p.m. for the Recto – Cubao route.