LUCENA CITY — Work on the 57-kilometer South Luzon Expressway-Toll Road 4 (SLEx-TR4) extension will start this month after delays that spanned the terms of six presidents, said Quezon Gov. David Suarez.
Suarez, during a meeting of the Provincial Development Council last week, said the Department of Public Works and Highways (DPWH) was finalizing the groundbreaking schedule before actual construction started for the project extending SLEx from Sto. Tomas town in Batangas province to Lucena City.
The project is divided into five sections: Sto. Tomas to Makban in Laguna (10.58 km); Makban to San Pablo City (12.2 km); San Pablo to Tiaong, Quezon (8.1 km); Tiaong to Candelaria, Quezon (14.4 km); and Candelaria to Lucena (12.3 km).
ROW problems
The SLEx extension project, its proponents said, will cut travel time between Santo Tomas and Lucena from the current three hours to just an hour.
During the recent Meet Inquirer Multimedia forum, Public Works Secretary Mark Villar confirmed that the SLEx-TR4 would push through after the DPWH acquired a “significant portion” of road right of way (ROW) for the project.
The extension of the expressway to Quezon was first planned during the administration of former President Ferdinand Marcos and was approved during the administration of former President Fidel Ramos in the 1990s.
Groundbreaking
The project broke ground during the term of former President Gloria Macapagal-Arroyo.
But the settlement of the ROW among landowners has been preventing construction work to proceed.
To help the DPWH resolve the SLEx-TR4’s ROW issue, Suarez initiated a meeting with 699 landowners from Tayabas City and the towns of Sariaya, Candelaria and Tiaong in August last year.
“The meeting hastened the process and issuance of [entry] permits … by the landowners. Without that permit, the contractor would not be able to start the road construction,” Suarez said. —Delfin T. Mallari Jr.