3rd Dalian train tested if MRT-compatible

/ 05:26 AM January 24, 2019

A third Dalian train started operating on the Metro Rail Transit (MRT) 3 tracks on Wednesday morning as part of a series of tests to determine whether it could be added to the regular fleet.

MRT 3 management director Michael Capati said the train would carry passengers from 6 a.m. to 9 p.m. until Feb. 1 for its 150-hour validation testing.

ADVERTISEMENT

Earlier, the Dalian train completed the 1,000-km commissioning test, one of several set by the Department of Transportation to determine its compatibility with the tracks.

During the commissioning test, which is conducted when the MRT 3 has ceased operations for the day, the train must be operated without any passengers for a total of 1,000 km. Afterward, it will move on to the next phase which is the 150-hour validation testing.

FEATURED STORIES

Only two of the 16 brand new China-made trains have so far completed the validation testing. The first was deployed from Oct. 23 to Nov. 21, after the DOTr concluded that the Dalian trains were safe and useable despite minor issues with spare parts. The second ran from Dec. 11 to Dec 23.

Should these two pass the test, only then would they be added to the regular MRT 3 fleet, Capati said.

The train system  is set to undergo a 43-month-long rehabilitation starting March—not February as earlier projected.

Before the tests, the Dalian trains had languished in the MRT 3 depot for about three years since their purchase under the Aquino administration.

An independent audit by TUV Rheinland found that the 48 light rail vehicles comprising the 16 Dalian trains did not follow some of the specifications in the terms of reference. However, TUV Rheinland said that with some minor modifications, the trains would be safe to use. —Krixia Subingsubing

ADVERTISEMENT
Read Next
LATEST STORIES
MOST READ
Don't miss out on the latest news and information.
View comments

Subscribe to INQUIRER PLUS to get access to The Philippine Daily Inquirer & other 70+ titles, share up to 5 gadgets, listen to the news, download as early as 4am & share articles on social media. Call 896 6000.

TAGS: Dalian trains, Michael Capati, MRT 3
For feedback, complaints, or inquiries, contact us.
opinion

Cleansing and upgrading Customs

April 22, 2019 09:07 AM

opinion

Mudslinging as a presidential pastime

April 22, 2019 09:06 AM

opinion

Titanic blunders

April 22, 2019 09:05 AM

opinion

The ‘evil vices’ of the poor

April 22, 2019 09:04 AM




© Copyright 1997-2019 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.