Worker’s fatal plunge mars Ayala Bridge reopening | Inquirer News

Worker’s fatal plunge mars Ayala Bridge reopening

The reopening of Ayala Bridge to traffic on Monday was marred by a work site accident that killed one of the men rushing to finish the rehabilitation of the structure.

The fatality was identified by the Manila Police District as Zaldy dela Torre, a 35-year-old welder employed by contractor Amsteel Structures Inc.

Initial police reports showed that Dela Torre was attaching a “fire catch” to a scaffolding at an elevated section of the bridge, as a safety measure to prevent welding sparks from falling on people or vehicles on the ground, when he lost his balance and fell, hitting the pavement head first.

ADVERTISEMENT

The accident happened around 2:30 p.m. Dela Torre was rushed to Philippine General Hospital, where he was declared dead on arrival.

FEATURED STORIES

An investigation showed that Dela Torre was last seen wearing a safety harness but that he apparently failed to attach this to any of the safety cables hanging from the bridge.

Police said the victim suffered a fracture in the skull as well as injuries in the body.

BLOOD MARKS THE SPOT   A welder’s death marked the partial reopening of Ayala Bridge to traffic  on Monday. Police said the worker was attaching  a safety net  at an elevated portion of the bridge when he lost his balance and fell head first. JILSON SECKLER TIU

BLOOD MARKS THE SPOT A welder’s death marked the partial reopening of Ayala Bridge to traffic on Monday. Police said the worker was attaching a safety net at an elevated portion of the bridge when he lost his balance and fell head first. JILSON SECKLER TIU

Meanwhile, after almost three months since the repairs started, the bridge was partially reopened Monday but authorities limited entry to light vehicles.

Reynaldo Tagudando, director of the Department of Public Works and Highways (DPWH) for the National Capital Region, said trucks and heavy vehicles would be allowed once full rehabilitation is achieved in September.

For now, just two out of the three lanes on both directions are open to traffic, he said.

Tagudando said some aspects of the rehab project were yet to  be finished, like the post-tensioning of the beams and the installation of dampers to make the structure more stable.
The DPWH has set aside P447.95 million for the upgrade of the bridge, which last saw major repairs in 1957.
The 139-meter-long structure on the Pasig River was also raised by 70 cm to allow more headroom for barges and other vessels.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Accident, Ayala Bridge, bridges, Manila

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.