Coal plant delay due to blackout

/ 01:44 AM April 22, 2015

DAVAO CITY—Aboitiz firm Therma South Inc. (TSI) has cited the April 5 blackout that plagued Mindanao as reason for the delay in the commissioning of Unit 2 of its coal-fired power plant in Barangay (village) Binugao in Toril district here.

The unit, with a capacity of 150 megawatts, would have been put online this month, but the power outage, which the National Grid Corp. of the Philippines attributed to a glitch in a switch in Agus in Lanao, damaged the facility’s boiler, TSI president and chief executive officer Benjie Cariaso Jr. said.

“The disruption damaged the auxiliary components of its boiler,” Cariaso said.

“The damage will delay the commercial operation of Unit 2 by about 10 months,” he said, pointing out that repair work on the boiler could last that long. Judy Quiros, Inquirer Mindanao

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Aboitiz, coal-fired plant, News, Regions

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.